Monday, March 17, 2008

Raasay Progress


Another week starts and the lights are still the spanner in the works! How much time and effort does it take to get them sorted to everyone's satisfaction? We really wanted to be forward thinking with them, being energy efficient, nice looking, fit for purpose etc, but, there seems so many conflicting inputs we are all a bit confused! If you have any ideas/expertise to get us over the impasse please tell us ASAP.

David,Freya, Finn and Leia are in their new house and enjoying the experience outside Raasay. Finn has fitted into the school effortlessly considering the protestations beforehand. He gets Art, Swimming, Music, Drama every week which he enjoys. He has made plenty new friends and I am sure they will soon never be out of the house. Leia goes to Gaelic nursery and now has more Gaelic than Mum and Dad!

Getting nearer to the "Comrie" Extravaganza so the usual pre-season preparations are well underway.

Better go and tackle the lights etc. etc

Friday, March 7, 2008

Turf cutting for new Raasay Ferry Terminal

Its been a wet and windy week here on Raasay, but the rain managed to stop for a brief moment today. As you may or may not be aware work is about to commence on the construction of the new ferry terminal at Chruchton Bay, below Raasay House.

To mark this occasion the chairman of transport, representatives for highland council and contractors from Balfour Beatty civil engineering performed a turf cutting ceremony with the children from the Raasay Primary School.

It was a low key even that lasted about 20 minutes before everyone went for a well needed cup of coffee to warm them up.....



Hi everyone, sorry for the lack of updates but it has been a busy time for us.. You would of thought that being closed would mean a smaller work load...well that's anything but true. We are busier than normal to be honest.

Anyway we had a site visit to Raasay House last week to check on the progress of the redevelopment. We drove up to the house, checked into the ROK site office where we had to put on our steel capped boots, fluorescent vests and hard hats and then escorted around the building; the building is currently in a pretty sad state and basically a building site.

Parts of the roof have been exposed to sort out rot problems, walls have been demolished, floor boards raised, ceilings pulled down, courtyards dug up the list goes on. The works to the east wing roof should be finished soon and then the scaffolding will be erected around the front of the house and the west wing. I will upload some photos once that has happened. In the mean time enjoy a few of our pics from our site visit last week.


The old Kitchen...now demolished and ready to make way for the new office....



Inspecting the the east wing roof....hmmm......



New entrance way has been made into the main dining room.....



Who would of thought that the staff shower room had a fireplace in it....



Pic of scaffolding on the east wing....